Foreword The commissioning is performed after the hardware installation
The commissioning ensures the RNC works properly as designed
RNC commissioning procedure
Commissioning RNC hardware
Commissioning software loading
Verifying all interfaces
Verifying RNC services
Integrating the RNC into M2000
Page3Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
References
《 RNC Commissioning Guide 》
Page4Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Objectives Upon completion of this course, you will be able to:
Describe the procedure of RNC commissioning
Perform the steps in RNC commissioning
Page5Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Contents
1. Introduction to RNC Commissioning
2. Procedure of RNC Commissioning
Page6Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Introduction to RNC Commissioning Definition of RNC Commissioning
The commissioning of equipment, RNC loading, interfaces,
and services after hardware installation
To ensures that the RNC works as designed
RNC Commissioning Prerequisites
Passing hardware installation acceptance and powering-on
test
At least one NodeB and one set of CN equipment available
Page7Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Introduction to RNC Commissioning RNC Commissioning Preparations
BAM and LMT application software are ready
License file is ready
MML command script for initial configuration is ready
Page8Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Contents
1. Introduction to RNC commissioning
2. Procedure of RNC commissioning
Page9Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Contents
2. Procedure of RNC commissioning
2.1 Commissioning RNC Equipment
2.2 Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)
2.3 Handling Alarms During RNC Commissioning
2.4 Verifying RNC Services
2.5 Integrating the RNC into the M2000
2.6 Creating RNC Scheduled Tasks
2.7 Checking RNC Commissioning Results
Page10Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC commissioning Commissioning RNC Equipment
Step 1 Commissioning BAM
Install the BAM application in the active workspace
Check the operation of the BAM application
Step 2 Commissioning LMT
Install LMT application
Connect LMT to the BAM
Start the local maintenance terminal
Page11Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC commissioning Commissioning RNC Equipment
Step 3 Loading RNC software and data file
Generating RNC data file
– Clear the data in the BAM database (RST DATA)
– Generate the data file in offline state (SET OFFLINE & FMT DATA)
DB
BAM
FormatFAM board
Resetto load
ConfigurationManagement
module
MMLConfiguration
command
*.dat
Configuration console
Page12Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC commissioning Commissioning RNC Equipment
Step 3 Loading RNC software and data file
Setting RNC loading parameter (SET LODCTRL )
Loading RNC
– Reset RNC (RST SYS)
– The boards automatically load software and data file from the
BAM
– Start the loading progress window to monitor the loading
process
Page13Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Commissioning RNC Equipment
Step 4 Verifying the license
Save the license in BAM Active Workspace Installation
Directory\FTP\License
Activate the license (ACT LICENSE)
Check the license consistency between host and BAM (CMP
LICENSE)
Display the configuration of license (DSP LICENSE)
Step 5 Verifying Switchover Between Active and Standby
Boards (SWP BRD)
Page14Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)
The protocol structure of terrestrial interfaces
TransportNetwork
Layer
Transport NetworkUser Plane
Control Plane User Plane
Transport NetworkUser Plane
Transport NetworkControl Plane
RadioNetwork
Layer
SignalingBearer
Physical Layer
SignalingBearer
DataBearer
Application Protocol
User Data
ALCAP
Page15Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)
Check the status of different objects
Verifying Iub interface
Checking physical link (DSP E1T1, DSP ETHPORT)
Checking control plane (DSP SAALLNK, DSP SCTPLNK, DSP
IUBCP)
Checking user plane (DSP AAL2PATH, DSP IPPATH)
Page16Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Verifying interfaces
Verifying Iub interface
Checking management plane
– To be sure NodeB can be operated at remote end
Checking cell status (DSP CELL)
Verifying Iu-CS, Iu-PS and Iur interfaces
The procedures and commands are similar with those in Iub
interface
Page17Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Handling Alarms During RNC Commissioning
Clearing the alarms if something wrong happen
Verifying RNC Services
To be sure RNC can provide services defined in license file
Basic services
– Voice service, CS stream service, PS service, mobility
management, and OM management
Feature services
– Inter-system handover, HSDPA service, HSUPA service, MBMS
service, and location service
Page18Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.
Procedure of RNC Commissioning Integrating the RNC into the M2000
Creating RNC Scheduled Tasks (back up tasks)
Checking RNC Commissioning Results