Urban Land / Master Planning Architecture
IBI Group - Core Disciplines
Land Use Planning
Urban Design
Landscape Architecture
Urban & Regional Development
Economic/Financial Analysis
Office, Commercial & Residential
Educational & Institutional
Medical & Research
Hospitality
Transportation Facilities
Name of Presentation
Transportation (Metro, LRT, BRT & HSR) Intelligent Transport Systems
IBI Group - Core Disciplines
Multi-Modal Transportation
Strategic Planning
Physical Planning & Design
Operational Planning
Transportation and Land Use
Transit-Oriented Development
Communication Systems
Intelligent Transport Systems
Revenue Collection Systems
Traffic & Transit Management Centres
Smart Cities/Intelligent Buildings
Security Systems
Name of Presentation
Mysore ITS – Implementation Challenges
by Shan Venkat, Senior Transportation Engineer
IBI Group
July 13, 2012
Structure
• Introduction
• Project Learning
• Conclusion
INTRODUCTION
6
Introduction: Components & Scope
• AVL
• Real-Time PIS (ETA & ETD)
• In-Vehicle Display
• Voice Announcement
• CCS
• MIS Reports
• EMS
• Training
Components
7
Scope500 buses
105 bus shelters
45 platforms
6 bus terminals
PROJECT LEARNING
8
Organization Structure
Impact
• Multi level monitoring – Close Co-ordination with City Administration, PMU, WB
Consultants, State Govt. etc
• Capacity building – In-depth study, thread-bear discussions and knowledge
transfer
• Sound Management Review Techniques – Weekly Meetings, Monthly
Steering Committee Meetings, Field visits, Adhoc meetings, consultations with PMC etc. So
far 11 Steering Committee Meetings headed by Managing Director, KSRTC and 19 Weekly
Review Meetings headed by Head-PIU have been held with circulation of meeting
proceedings for action points.
KSRTC
Vendor M & EPMC
May 14, 2011 Aug 26, 2011 Apr 2, 2012
Solution Provider- Project Phases & Activities
Build Pilot Rollout
Program Management
• Site Survey• Site Plan Sign-off• System Study &
Review SRS• Procurement of
Hardware• Installation and
Commissioning of Hardware and Applications
• Customization of Application
• Installation of VMU & Displays
• Integration testing of Application
• Run Pilot for selected Bus routes
• Performance tuning• Generate MIS
Reports• Basic training – Pilot
Phase
• ITS Application configuration
• Data Management• Delivery and
Installation of Remaining VMU, Display Units
• Commission DR & Testing
• Backup & Restore• System fine tuning• Training • User Acceptance
Test (UAT) & documentation
Software
Infrastructure
VMU + Display Units
EMS
Operations
Training
10
IBI Group - Project Phases & Activities
Design/Build Procurement Implementation
• Power calculations
• CCS room design• Communication
bandwidth calculation
• Database sizing• Software
specifications• Hardware
specifications• Design document
for VMU and PIS• Test plans for
VMU, PIS, & SFAT• ETA algorithm• EMS• Software
application development
• FAT for custom hardware (VMU and PIS )
• Software FAT• Procurement of
off-the-shelf and custom hardware
• Software procurement
• Deliveries for full system
• Full system hardware installation
• Full system software installation
• ITS Application configuration
• System Integration
• POP & WIR• System
Acceptance• Roll out
• Kick off meeting• Site Survey• Site Plan Sign-off• System Study &
Review SRS• Project Plan• Implementation
Plan
Planning
Solution Provider - Implementation Plan ( Initially 30 tasks)
IBI Group - Revised Implementation Plan (185 tasks)
GIS Map – Operational Requirements
What should the GIS map display?
Installation & Types of Buses
Installation – Equipment Locations
• End user acceptance and usage
• Understanding of operations
Civil Works
• Multi-Organization Coordination
– Bus Shelter Structure
– Raw Power @ Bus Shelters
– Locations
• CCS Room
– AC Ducting Delay – 1 month
– Flooring Delay – 1 month
KSRTC – Mysore ITS17
Project Planning – Route & Bus Stop Validation
Incomplete Trips
Incomplete Trips
U-Turn @ KRS Stop
Video wall
BEFORE NOW
Samsung 50 inch TV Christie Videowall
(bezel is more than 4 cm) (bezel is less than 7 mm)
Functional Vs. Technical Requirements
• Power Requirements
– UPS: Original (10 KVA + 10 KVA); Final (20 KVA + 20 KVA)
– Diesel Generator: Original (30 KVA); Final (70 KVA)
• Passenger Information Signs (PIS) – Readability 3m to 30m
– Size: Original – Existing Vendor Solution, Final – As per RFP
– Pitch : Original - 10mm, Final – 10mm
– Color: Original – red; Final - yellow
– Font (Kannada): Original – Baraha; Final – Nudi 05
Planning & Documentation
• SRS – Detailed SRS (11 revisions) has been completed.
• Project Plan – Detailed project plan that looks at operations not software & hardware
• Site report – detailed survey identifying the gaps and site requirements for the project prior to implementation.
• In-bus equipment installation guide – An installation guide detailing the locations for VMU, In-bus PIS, timer, amplifiers, speakers and battery has been identified (close coordination with drivers and other crew) and been documented for all the seven types of buses.
• Testing – A systematic testing in terms of FAT followed by field tests is in place for the VMU and PIS display boards. Prior to this, VMU, PIS and SFAT test plans (5 revisions) has been completed.
• SMS plan – Detailed SMS plan created.
• Design documents/Calculations – PIS design document, Power calculations document, communication bandwidth is in place.
• Training Plan for Crew and other Stakeholders
Project Learning - continued
• Acquaintance with World Bank Procurement Procedures
• Identification and Construction of bus shelters in time
• Ensuring power supply at bus shelters
• Placement of PMC and M&E services in time
• Setting right expectations
• Exposure to the crew about the system in advance
• Location and designing of CCS
• Budgeting of project components should have practical
approach
• MIS report prepared with close coordination with the client by understanding
their needs and requirements
Conclusion
• Capacity Development
– The adequacy of the resources need to be understood, identified and
assigned accordingly. The skill set of resources is another major issue.
• Ground Realities
– Knowing when you are hitting a brick wall and changing direction is
important.
– Importance of Planning vs. Jugaad
• Culture Change
– The culture of “yes sir’’ needs to change.
• “Devil is in the detail”