  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 1 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    SOUTHERN PERU COPPER CORPORATION

    RANDOM WAGON UNLOADING SYSTEM

    SITE INSTALLATION METHOD STATEMENT

    REVISION RECORD

    Revision

    No.

    Description Originated Checked Approved

    00 First Issue for quotation purposes. DMR

    Aug/2013

    01

    Updated in line with latest drawings.

    Issued to SPCC for site planning purposes.

    DMR

    16Jan2014

    JWH

    30:Jan:2014

    JWH

    30:Jan:2014

    INTELLECTUAL PROPERTY

    The information in this document was prepared using Intellectual

    Property owned by Schade Lagertechnik GmbH. This is confidential

    proprietary information and remains the exclusive property of

    Schade. The document is for use solely in connection with the

    performance of Schades Contracts.

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 2 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    EXPLANATORY NOTES - READ BEFORE USE

    1. The objects of this Method Statement are

    - to specify the Operations necessary to perform works trial assembly, works test, site installation, site commissioning or acceptance tests, as appropriate,

    - to specify where procedures are to be approved by Schade before use and where separate record documents are to be generated,

    - to state the requirements for witness, inspection and document review by Schade, - to make provision for recording the satisfactory completion of requirements.

    2. Listed at appropriate places within this Method Statement are the drawings and documents needed to complete

    the work. Where the Issue Level has been left blank the SPCC, installer or Schade Technical Advisor, as

    appropriate, is to enter the Issue Level of the drawings and documents provided by Schade.

    3. Listed within the main body of the Method Statement are the Operations necessary to complete the work.

    SPCC, the installer or Schade Technical Advisor, as appropriate, is to sign off and date in the "Operation

    Complete" column each operation as it is completed satisfactorily.

    4. The symbol X is used in the column headed "Document required" to denote a requirement for a written

    procedure or a specific record. In addition, the Symbol AP is used to denote where Schade approval of a

    procedure is required before implementation. SPCC, the installer or Schade Technical Advisor is to record

    beneath these symbols the identity of the procedure or record document so produced.

    Reference is also to be made in this column to the identity of any Technical Query or Concession, approved by

    Schade, which represents a departure from specified requirements.

    5. Symbols for Schade verification are shown in the column headed "Verification" according to the following

    Code:

    A1 - 100% inspection R1 - 100% Document Review W1 - 100% Witness of Operation

    A2 - Sample inspection R2 - Sample Document Review W2 - Sample witness of Operation

    SPCC or the installer, as appropriate, is to obtain the Schade Technical Advisors counter-signature beneath the

    symbol as required and as work proceeds.

    An Operation shown as A1 must be signed off before proceeding with the next Operation.

    An Operation shown as W1 or W2 is to be performed in the presence of the Schade Technical Advisor.

    6. Operations are to be performed in the sequence written unless otherwise agreed by the Schade Technical

    Advisor.

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 3 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    CONTENTS

    I. INTRODUCTION & GENERAL INSTRUCTIONS ......................................................................................................... 4

    II. GENERAL LIST OF DRAWINGS & DOCUMENTS REQUIRED FOR USE WITH THIS METHOD STATEMENT .................. 5

    III. METHOD STATEMENT........................................................................................................................................... 7

    1. INTRODUCTION .................................................................................................................................................... 8

    2. FOUNDATIONS ................................................................................................................................................... 11

    3. TIPPLER & RUN-BACK STOP INSTALLATION ........................................................................................................ 13

    4. DIMENSIONAL CHECK ......................................................................................................................................... 34

    5. FINAL INSPECTION .............................................................................................................................................. 34

    6. FINAL DOCUMENT CHECK ................................................................................................................................... 34

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 4 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    I. INTRODUCTION & GENERAL INSTRUCTIONS

    This schedule covers the site installation of the Schade Wagon Tippler and Exit Run-Back

    Stop as shown on Schade drawing 6003_02_003, General Arrangement of Wagon

    Unloading System.

    It is mandatory that all items have completed the manufacturing and inspection process.

    It is the responsibility of the reader to ensure that all documents used during assembly and

    inspections are at the latest issue level.

    For a complete set of drawings refer to Schade document, 6000_00_003 - Family Tree of

    Assemblies (plus associated parts lists), which is also to be used to reference Schade

    drawing numbers.

    Where measurement and recordings are required in this schedule they must be completed

    and then returned to Schade, as a record document.

    If any items (bearings, motors, power packs, cubicles etc.) have been in long term storage,

    they must be checked to suppliers requirements.

    All personnel working on the site must have the appropriate qualification and work

    experience for the trade for which they are employed in accordance with Peruvian

    legislation and local employment rules.

    The Company employed to carry out the mechanical installation work should have had a

    minimum of 5 years experience in erecting equipment of this type or similar.

    The Site Manager employed by them should also have a similar period of experience

    working on similar plant.

    All site personnel should be aware of any Safety Legislation that is appropriate to working

    on a Peruvian Site and be inducted on the Site Safety Procedures if appropriate.

    The text in this document for the total installation should be read prior to commencement

    of the work. The installation method and sequence given in the text is recommended but

    not mandatory.

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 5 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    II. GENERAL LIST OF DRAWINGS & DOCUMENTS REQUIRED FOR USE WITH THIS METHOD STATEMENT

    If they are not already shown in the right hand column, the Issue Levels of Drawings and

    Documents provided are to be entered by the Installation Contractor or Schade Technical

    Advisor, as appropriate.

    Drawing/Document

    Number

    Title Rev.

    6000_00_003 Family Tree of Assemblies 05

    6003_02_003 GA of Wagon Unloading System 00

    6035_02_007 Assembly of 14m Pivot Frame Tippler 00

    6095_02_002 Assembly of Pivot Frame Tippler Structure 02

    6561_02_007 End Ring Structure (Driven) 01

    6562_02_007 End Ring Structure (Driven) 01

    6565_02_009 Side Beam Structure 02

    6186_02_002 Assembly of Tippler Ballast 00

    6968_00_001 # Tippler Structure Shop Assembly Survey Drawing 00

    20.312_D15 # Tippler Shop Assembly Method Statement 02

    #, marked up/signed workshop copies

    6130_02_003 Assembly of Tippler Fixed Blocking 00

    6104_02_009 Assembly of Tippler Spill Plates and Wear Plates 00

    6102_02_006 Assembly of Tippler Clamp 02

    6101_02_003 Assembly of Tippler Main Pivot (Non-Locating) 00

    6101_02_004 Assembly of Tippler Main Pivot (Locating) 00

    6100_02_003 Assembly of Platform 01

    6566_02_007 Platform Structure 01

    6198_02_002 Assembly of Platform Walkways 00

    6115_02_003 Assembly of Platform Support 00

    6103_02_006 Assembly of Tippler Drives (Left Hand) 02

    6103_02_007 Assembly of Tippler Drives (Right Hand) 02

    6723_02_001 Thrust Pad 00

    6105_02_003 Assembly of Tippler Cable Loop 00

    6106_02_003 Assembly of Tippler Limit Switches 00

    6107_02_003 Assembly of Tippler Clearance Sensors 00

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 6 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    6133_02_001 Assembly of Stockpile Sensors 00

    6108_02_003 Assembly of Grout and Packing 00

    6058_02_004 Assembly of Exit Run-Back Stop (Manual) 01

    6460_00_009 Wagon Unloading System Foundation Details and Loadings 02

    6974_00_001 Transport Drawing (LH End Ring) 00

    6974_00_002 Transport Drawing (RH End Ring) 00

    6974_00_003 Transport Drawing (Side Beam) 00

    6974_00_004 Transport Drawing (Platform) 00

    6974_00_005 Transport Drawing (Clamp) 00

    6974_00_006 Transport Drawing (Drive Assembly LH) 00

    6974_00_007 Transport Drawing (Drive Assembly RH) 00

    6974_00_008 Transport Drawing (Support Roller LH) 00

    6974_00_009 Transport Drawing (Support Roller RH) 00

    6400_00_002 Assembly of Tippler Hydraulics 02

    plus Bosch Rexroth Hagglunds drawings (see Family Tree) and

    instructions

    6410_00_002 Assembly of Tippler and Run-Back Stop Lubrication 01

    plus Bijur Delimon drawings (see Family Tree) and instructions

    6340_00_002 Assembly of Tippler and Run-Back Stop Electrics 02

    plus Iconsys drawings (see Family Tree) and instructions

    20.312_D26 Electrical Site Installation Method Statement 00

    6495_00_001 Assembly of Dust Suppression System 00

    plus Nalco Enviroflo drawings (see Family Tree) and instructions

    20.312_D04 Manufacturing Specification 04

    6975_00_001 Tippler Erection Sequence Diagram 00

    Schade Packing List

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 7 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    III. METHOD STATEMENT

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 8 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    1. INTRODUCTION

    1.1 All components must be checked against the

    Schade packing list.

    1.2 All components are to be checked for any damage caused by handling during transit.

    Repair of any major steelwork damage is to

    be referred to Schade design office.

    Where appropriate, ensure all rotating or sliding

    contact surfaces are liberally greased during

    assembly.

    1.3 All site work must conform to Schade

    document 20.312_D04, Manufacturing

    Specification.

    All bolted joints are critical and their assembly

    must comply with section 5 of 20.312_D04.

    Refer also to Schade drawings for any specific

    joints requirements.

    All torque wrenches must be calibrated

    immediately before use on this project.

    Check the condition, size and grade of all bolts,

    nuts and washers with drawing requirements

    before installation.

    1.4 Any damaged paint work is to be repaired in accordance with paint suppliers instructions.

    The final paint coat is to be applied during

    erection at appropriate stages determined by the

    erection contractor in accordance with the paint

    suppliers instructions.

    1.5 Check that all bearings and bushes are primed

    with lubricant.

    During workshop assembly, temporary grease

    nipples have been installed to lubricate bearings

    and bushes. These are to be removed when the

    Schade

    packing list

    Calibration

    certificates

    A1

    A1

    A1

    A1

    A1

    when

    they are

    installed

    A1

    A1

    A1

    A2

    A2

    R1

    A2

    A2

    W2

    A1 Main

    Pivots

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 9 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    centralised lubrication system is installed.

    1.6 Prior to the installation of any hydraulic equipment, ensure that all components are

    delivered & in their correct/un damaged

    condition in accordance with the Bosch

    Rexroth Hagglunds requirements, i.e. pipes

    have been pickled, cleaned and ends are

    capped.

    1.7 Prior to the installation of any lubrication equipment, ensure that all components are

    delivered & in their correct/un damaged

    condition in accordance with the Bijur

    Delimon requirements.

    1.8 Prior to the installation of any dust

    suppression equipment, ensure that all

    components are delivered & in their

    correct/un damaged condition in accordance

    with the Nalco Enviroflo requirements.

    1.9 During site installation, welding to main

    structures is not allowed unless shown on a

    Schade drawing and approved in writing

    by Schade design office.

    1.10 Any deviations to the tolerance requirements

    of this method statement and Schade

    drawings are to be recorded and reported to

    Schade design office before proceeding.

    1.11 The Tippler structure has been workshop

    assembled and dimensionally inspected in

    accordance with Schade drawing and

    document:-

    6968_00_001, Tippler Structure Shop Assembly

    Survey Drawing.

    20.312_D15, Tippler Shop Assembly Method

    Statement

    All site erection work must use the marked

    up/signed workshop copies.

    Schade

    packing list.

    Suppliers

    documents

    Schade

    packing list.

    Suppliers

    documents

    Schade

    packing list.

    Suppliers

    documents

    X

    Marked up

    drawings &

    documents

    Workshop

    copy

    Workshop

    copy

    A1

    A1

    A1

    A1

    R1

    R1

    A2

    A2

    A2

    A1

    R1

    R1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 10 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    The Tippler structure has been part dismantled as

    shown on the following Schade drawings:-

    6974_00_001, Transport Drawing (LH End Ring)

    6974_00_002, Transport Drawing (RH End Ring)

    6974_00_003, Transport Drawing (Side Beam)

    6974_00_004, Transport Drawing (Platform)

    Prior to dismantling the Tippler structure in

    the workshop, all joints have been match

    marked and recorded. This match marking

    must be worked to for site erection. See also

    workshop photographs.

    1.12 In addition to the Tippler structure, the following Schade drawings show other

    workshop assemblies that have not been part

    dismantled:-

    6974_00_005, Transport Drawing (Clamp)

    6974_00_006, Transport Drawing (Drive Assy

    LH)

    6974_00_007, Transport Drawing (Drive Assy

    RH)

    6974_00_008, Transport Drawing (Support

    Roller LH)

    6974_00_009, Transport Drawing (Support

    Roller RH)

    1.13 The Tippler Fixed Blocking (6130_02_003) and Spill & Wear Plates (6104_02_009) have

    both been shop assembled to the Side Beam,

    match marked and then fully dismantled for

    transport.

    1.14 Main structures do not include lifting points as the available cranage is not known to

    Schade. It is the responsibility of the site

    erection contractor to correctly handle the

    Workshop

    records

    Workshop

    records

    R1

    R1

    R2

    R2

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 11 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    structures taking into account the mass &

    centre of gravity position. If in doubt, send

    lifting proposals with sketches for Schade

    design office review.

    2. FOUNDATIONS

    2.1 Ensure that all foundation levels and details correspond to the requirements shown on

    Schade drawing:-

    6460_00_009, Wagon Unloading System

    Foundation Details and Loadings.

    Note the civil contractor made an error with

    the casting of the Tippler Main Pivot pillars

    (see section D-D on above drawing) which was

    accepted by Schade. Refer to SPCC records

    for this error.

    2.2 A complete check is to be made of all levels, dimensions and requirements shown on the

    Schade drawing to ensure compliance. Any

    variations are to be recorded & reported to

    Schade design office before proceeding.

    2.3 Foundation levels and surface conditions are critical at the following points:-

    Tippler Main Pivots (x2) and Drives (x2), see

    section D-D on above drawing.

    Platform Supports (x2), see section E-E on above

    drawing.

    2.4 Check that all cast in studs are dimensionally as required and allow side movement as

    shown on the above drawing. See sections K-

    K, J-J and H-H.

    Check that these stud groups are positioned to

    within the tolerance requirements of drawing

    dimensions and note 3.

    2.5 At least 3x permanent datum plates are to be cast in as shown on the above drawing. Mark

    all relevant centre-lines and elevation levels

    Mark up copy

    of drawing

    6460_00_009

    A1

    A1

    A1

    A1

    A2

    R1

    A1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 12 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    on the foundation datum plates. Additional

    datum plates are to be fitted, if required to aid

    installation.

    Using these datum plates, determine the

    following:-

    Centreline of main railway track.

    Centreline of Tippler (perpendicular to main track).

    Centreline of both End Rings.

    Top of concrete (TOC) level +5.321

    2.6 Terminology used in this document (see Schade drawings 6460_00_009 &

    6975_00_001) is:-

    Non tip side of Tippler is towards building columns K12 to K17 (parallel with main

    track on side of Tippler where trackside

    operators work).

    Tip side of Tippler is towards building columns J12 to J17 (parallel with main track

    on side of Tippler where payload is

    discharged).

    Left hand end (LH) of Tippler is towards building columns K17 & J17 (full wagon

    entry end).

    Right hand end (RH) of Tippler is towards building columns K12 & J12 (empty wagon

    exit end).

    2.7 Where jacking screws are called for on Schade drawings to support/level components

    on the foundations, an 80 x 80 x 6mm thick

    plate is to be positioned centrally below them

    to spread the load onto the concrete per

    Schade drawing 6108_02_003.

    2.8 Where grouting is shown on Schade drawing 6108_02_003, this is to be supplied by the

    installation contractor.

    The grout must be of suitable strength to

    Grout

    suppliers

    instructions

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 13 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    withstand the applied loads as given on Schade

    drawing 6460_00_009, Wagon Unloading System

    Foundation Details and Loadings.

    3. TIPPLER & RUN-BACK STOP INSTALLATION

    The Tippler erection is to be carried out in the

    sequence detailed below (unless otherwise agreed

    with the Schade Technical Advisor) and as shown

    on Schade drawing:-

    6975_00_001, Tippler Erection Sequence

    Diagram.

    3.1 Initial positioning of Tippler Drives and Platform Supports

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 1)

    6103_02_006, Assembly of Tippler Drives (LH)

    6103_02_007, Assembly of Tippler Drives (RH)

    6115_02_003, Assembly of Platform Support

    6974_00_006, Transport Drawing (Drive LH)

    6974_00_007, Transport Drawing (Drive RH)

    6688_02_001, Drive Plinth

    6108_02_003, Assembly of Grout and Packing

    3.1.1 Install 6688_02_001 Drive Plinths (6103_02_006 and 6103_02_007 item 1) with jacking screws

    onto M30 foundation studs.

    Align Plinths to the following dimensions:-

    Top faces horizontal in both planes to within 1mm.

    X

    Record all

    dimensions

    R1

    A1

    R1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 14 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    Top faces level with each other to within 1mm.

    Top faces 2520mm below TOC. Note this is 40mm nominal below final

    level.

    Longitudinal (2220mm) centre line 68772mm from centre line of Tippler.

    Front face (1000mm) of top flange 1120 2mm tip side of centreline of main track.

    Install packers between concrete and underside of

    Drive Plinths to Schade drawing 6108_02_003.

    Hand tighten M30 nuts/washers on foundation

    studs.

    3.1.2 Install RH workshop sub assembled drives (6974_00_007 & 6103_02_007) onto plinth and

    assemble bolted joint to 20.312_D04.

    3.1.3 Install LH workshop sub assembled drives

    (6974_00_006 & 6103_02_006) onto plinth and

    assemble bolted joint to 20.312_D04.

    3.1.4 Check that all 4 pinions are free to rotate.

    Note - the brakes are supplied with screws

    installed which hold the brakes in the released

    position and allow the motor & brake assembly to

    be rotated. These screws are not to be removed

    until the hydraulics are installed and

    commissioned.

    Tippler structure rotation is to be restrained

    by chain blocks, chocks and/or tirfors etc., not

    the drive brakes.

    3.1.5 Sub assemble 6115_02_003 Platform Supports

    (x2) to drawing.

    3.1.6 Install Platform Supports with jacking screws and washers (item 6) onto M30 foundation studs.

    Align Platform Supports to the following

    dimensions:-

    X

    Drawing

    X

    All

    dimensions

    A1

    A1

    A1

    W1

    W1

    W1

    W1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 15 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    Top faces horizontal in both planes to within 1mm.

    Top faces level with each other to within 1mm.

    Top faces of support beams (item 1) 1270 1mm below TOC.

    Longitudinal (1970mm) centre line 5500 2mm from centre line of Tippler.

    Centreline of lower locating block (item 2) 755 1mm non tip side of centreline of main

    track.

    Install packers between concrete and underside of

    Platform Supports per Schade drawing

    6108_02_003.

    Hand tighten M30 nuts/washers on foundation

    studs.

    Do not weld washers (item 6) at this stage.

    3.1.7 Check installation of both Drives and both Platform Supports, and record all dimensions.

    3.2 Main Pivot Stools

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 2)

    6101_02_003, Assembly of Tippler Main Pivot

    (Non-Locating)

    6101_02_004, Assembly of Tippler Main Pivot

    (Locating)

    6685_02_002, Pivot Stool

    6968_00_001, Tippler Structure Shop Assembly

    Survey Drawing

    6108_02_003, Assembly of Grout and Packing

    6108_02_003, Assembly of Grout and Packing

    A1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 16 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    The installation of the Pivot Stools and Main

    Pivot Bearings is crucial to the Tippler

    operation.

    3.2.1 Install 6685_02_002 Pivot Stools (6101_02_003 and 6101_02_004 item 1) with jacking screws

    onto M30 foundation studs.

    Align Pivot Stools to the following dimensions:-

    Top faces horizontal in both planes to within 0.5mm.

    Top faces level with each other to within 1mm.

    Top faces 2700 2mm above TOC.

    Longitudinal (1370mm) centre line of LH stool 7910 2mm from centre line of Tippler.

    Longitudinal (1370mm) centre line of RH stool to longitudinal centre line of LH stool

    per workshop drawing 6968_00_001

    dimension recorded bearing housing

    centres.

    Transverse (450mm) centre lines 2450 2mm non tip side of centre line of main track.

    Transverse centre lines within 1mm of each other.

    Install packers between concrete and underside of

    Pivot Stools per Schade drawing 6108_02_003.

    Hand tighten M30 nuts/washers on foundation

    studs.

    3.2.2 Check installation of both Pivot Stools and record all dimensions.

    3.3 Left Hand End Ring Assembly

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 3)

    6101_02_003, Assembly of Tippler Main Pivot

    (Non-Locating)

    X

    All

    dimensions

    A1

    A1

    A1

    W1

    W1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 17 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    6974_00_001, Transport Drawing (LH End Ring)

    6748_02_001, Tippler Pivot Transport Bracket.

    3.3.1 Position the LH End Ring sub assembly (6974_00_001) onto its Pivot Stool with the End

    Ring centre line in the vertical plane.

    Notes-

    At some stage during this operation, the Transport Bracket (6748_02_001) will need

    to be removed. Care must be taken to ensure

    that the bearing seals are not damaged. Install

    temporary restraints if required.

    A check must be made on the rack to drive pinions meshing.

    See clause 3.8.2 re final positional accuracy.

    TOC down to bottom of End Ring toe slot is 578 2mm.

    Secure in position with supports and guy ropes.

    3.3.2 Assemble housing to stool joint and hand tighten.

    3.4 Right Hand End Ring Assembly

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 4)

    6101_02_004, Assembly of Tippler Main Pivot

    (Locating)

    6974_00_002, Transport Drawing (RH End Ring)

    6748_02_001, Tippler Pivot Transport Bracket.

    3.4.1 Position the RH End Ring sub assembly (6974_00_002) onto its Pivot Stool with the End

    Ring centre line in the vertical plane.

    Notes-

    At some stage during this operation, the Transport Bracket (6748_02_001) will need

    X

    Procedure

    X

    Dimension

    X

    Procedure

    A1

    A1

    A1

    R1

    W1

    A1

    A2

    A1

    R1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 18 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    to be removed. Care must be taken to ensure

    that the bearing seals are not damaged. Install

    temporary restraints if required.

    A check must be made on the rack to drive pinions meshing.

    See clause 3.8.2 re final positional accuracy.

    TOC down to bottom of End Ring toe slot is 578 2mm.

    Secure in position with supports and guy ropes.

    3.4.2 Assemble housing to stool joint and hand tighten.

    3.4.3 Check alignment and dimensions between End Rings (12400mm nominal).

    Check the condition of all internal and external

    plate surfaces (where splice plates will locate) on

    both LH and RH End Rings are to Schade

    document 20.312_D04.

    3.4.4 With reference to Schade drawing 6968_00_001, check that the workshop recorded end ring

    centres have been achieved.

    3.5 Side Beam

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 5)

    6565_02_009, Side Beam Structure

    6974_00_003, Transport Drawing (Side Beam)

    3.5.1 Remove the Splice Plates and review the overall Side Beam length against the End Ring inside

    dimensions recorded above.

    Check the condition of all internal and external

    plate surfaces (where splice plates will locate) are

    to Schade document 20.312_D04.

    Check the condition of the splice plate surfaces to

    Schade document 20.312_D04.

    X

    Dimension

    X

    Dimension

    A1

    A1

    A1

    A1

    A1

    A1

    A1

    A1

    A1

    A1

    A2

    A1

    A1

    A1

    R1

    R1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 19 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.5.2 Review workshop match marking for both joints.

    Workshop match marking must be adhered to

    for site assembly.

    Position internal Splice Plates inside Side Beam

    and secure.

    3.5.3 Lift the Side Beam and position between the End Rings obtaining equal gaps (4mm max.) at both

    ends. Use temporary supports as required.

    3.5.4 Before making the bolted joints and with reference to Schade drawing 6968_00_001, re

    check that the workshop recorded end ring

    centres have been achieved.

    3.6 Side Beam to End Ring Bolted Joints

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 6)

    6095_02_002, Assembly of Pivot Frame Tippler

    Structure

    6968_00_001, Tippler Structure Shop Assembly

    Survey Drawing

    The correct installation of these joints is

    crucial to the correct operation of the Tippler.

    100% contact must be achieved between all

    splice plates and the structure.

    3.6.1 Assemble and complete both joints in total accordance with Schade document 20.312_D04

    and Schade drawing 6095_02_002.

    3.7 Tippler Structure Check

    Refer to the following Schade drawings:-

    6968_00_001, Tippler Structure Shop Assembly

    Survey Drawing

    Workshop

    records

    X

    Procedure

    X

    Dimension

    R1

    A1

    A1

    A1

    R1

    R1

    A1

    R1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 20 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    6095_02_002, Assembly of Pivot Frame Tippler

    Structure.

    3.7.1 Check that Tippler structure is in total accordance with all Schade drawing and document

    requirements.

    Any deviations are to be reported to Schade

    design office before proceeding.

    3.8 Completion of Main Pivots

    Refer to the following Schade drawings:-

    6101_02_003, Assembly of Tippler Main Pivot

    (Non-Locating)

    6101_02_004, Assembly of Tippler Main Pivot

    (Locating)

    3.8.1 Complete the assembly of the housing to stool joints.

    Torque M42 bolts to SKF installation

    instructions.

    Do not grout pivot stools at this stage.

    3.8.2 Check and record the following dimensions:-

    Bearing housing centres

    (158203mm)

    Centre line main track to centre line LH

    pivot shaft (24502mm) #1

    Centre line main track to centre line RH

    pivot shaft (24502mm) #1

    TOC to centre line LH pivot shaft

    (31102mm) #2

    TOC to centre line RH pivot shaft

    (31102mm) #2

    Centre line LH pivot shaft to bottom of

    End Ring toe slot (3687mm) #3

    Centre line RH pivot shaft to bottom of

    End Ring toe slot (3687mm) #3

    Notes-

    Schade

    drawings and

    workshop

    records.

    SKF

    installation

    instructions

    A1

    A1

    A1

    A2

    R1

    W1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 21 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    #1, and within 1mm of each other.

    #2, and within 1mm of each other.

    #3, and within 4mm of each other. i.e. max. 4mm twist in structure.

    3.8.3 If all dimensions are correct, grout both Main

    Pivots and torque nuts on foundation studs and

    weld shear blocks per drawing requirements.

    3.9 Clamps

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 7)

    6102_02_006, Assembly of Tippler Clamp

    6974_00_005, Transport Drawing (Clamp)

    3.9.1 With reference to Schade drawing 6102_02_006

    section A-A, remove the Pivot Pin (Clamp Arm)

    item 6 from each Clamp assembly.

    Remove also the transport lifting beam

    (assembled in place of the hydraulic cylinder).

    3.9.2 Check that the underside of the Clamp Brackets

    and mating surfaces on the Side Beam comply

    with Schade document 20.312_D04 for these

    bolted joints.

    3.9.3 In accordance with the workshop match marking,

    position the Clamp Brackets (6102_02_006 item

    4) in their correct positions and assemble the

    Bracket to Side Beam bolted joints in accordance

    with Schade drawing 6035_02_007 and document

    20.312_D04.

    The correct installation of these joints is

    crucial to the correct operation of the Tippler.

    100% contact must be achieved at all Clamp

    Brackets.

    Workshop

    records

    A1

    A1

    A1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 22 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.9.4 Install Wear Plates (6102_02_006 items 17 to 45 inclusive), re install Pivot Pins and re install

    transport lifting beams.

    3.10 Fixed Blocking

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 8)

    6130_02_003, Assembly of Tippler Fixed

    Blocking

    3.10.1 Apply top coat of paint to all external surfaces of the Side Beam prior to fitting the Fixed

    Blocking and Spill & Wear Plates.

    3.10.2 In accordance with the workshop match

    marking, assembly the Fixed Blocking to Side

    Beam in accordance with Schade drawing

    6130_02_003 and document 20.312_D04.

    3.10.3 Assemble Rubber Liner (6130_02_003 item 7)

    to wooden blocking in accordance with drawing

    instructions.

    3.11 Spill and Wear Plates

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 9)

    6104_02_009, Assembly of Tippler Spill Plates

    and Wear Plates

    3.11.1 In accordance with the workshop match marking, assemble the Spill Plates and Wear

    Plates to Side Beam in accordance with Schade

    drawing 6104_02_009 and document

    20.312_D04.

    3.12 Tippler out of Balance

    At this stage of erection, the total mass of the

    Workshop

    records

    Workshop

    records

    R1

    R1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 23 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    rotating structure is 70.2 tonnes approx.

    The centre of gravity position is 600mm approx.

    towards the tip side, which means that the

    structure would rotate anti-clockwise (when

    viewed from the full wagon entry end) if not

    restrained.

    The angle of rotation to the balance point is 53

    approx. anti-clockwise.

    Under controlled conditions, rotate the Tippler to

    the balance point and secure at this angle.

    3.13 Alignment of Tippler Drives

    Refer to the following Schade drawings:-

    6103_02_006, Assembly of Tippler Drives (LH)

    6103_02_007, Assembly of Tippler Drives (RH)

    3.13.1 Using the jacking screws, raise each drive to obtain the correct rack/pinion gear meshing.

    Set this initially at 15mm (root gap) from pinion

    outside diameter (528mm) to rack root diameter

    (R5070mm). This equates to theoretical gear

    centres of 5349mm.

    Hand tighten Drive Plinths M30 foundation studs

    and adjust packers between concrete and

    underside of Drive Plinths as required.

    3.13.2 Under controlled conditions, rotate the Tippler

    back to the 0 angle to obtain TOC to bottom of

    End Ring toe slot of 578mm.

    Check meshing of pinion teeth in racks.

    Do not install Base to Bracket fitted bolts at this

    stage.

    3.14 Platform Sub-Assembly

    Refer to the following Schade drawings:-

    X

    Procedure

    X

    Procedure

    A1

    A1

    R1

    W1

    A1

    R1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 24 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    6100_02_003, Assembly of Platform

    6198_02_002, Assembly of Platform Walkways

    6974_00_004, Transport Drawing (Platform)

    6974_00_008, Transport Drawing (Support

    Roller LH)

    6974_00_009, Transport Drawing (Support

    Roller RH)

    6607_01_008, 115 lb AREMA Rail

    6625_02_007, Gantrail 9 Series Rail Clip

    (the weldable bases of the clips have been welded

    in position during workshop assembly)

    3.14.1 On levelled temporary supports adjacent to the Tippler, position the Platform Structure

    (6100_02_003 item 1). Scribe lines on the top

    surface for the longitudinal centre line, transverse

    centre line and end ring centres (14000 3mm).

    Note, the longitudinal centre line will be in line

    with the main track centre line.

    3.14.2 Assemble the LH and RH Support Roller

    assemblies (6974_02_008 and 6974_02_009) and

    the Upper Locating Blocks (6100_02_003 item

    18) to the Platform Structure in accordance with

    Schade drawing 6100_02_003 and document

    20.312_D04.

    Record the following dimensions:-

    Support Roller longitudinal

    centres (11000 3mm)

    Structure top face to underside

    of roller RH (1225mm)

    Structure top face to underside

    of roller LH (1225mm)

    Locating Block longitudinal

    centres (11000 3mm)

    A1

    A1

    A1

    A1

    W1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 25 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    Structure top face to underside

    of locating block RH

    (1070mm)

    Structure top face to underside

    of locating block LH

    (1070mm)

    RH locating block to RH roller

    (1510mm)

    LH locating block to LH roller

    (1510mm)

    Structure centre line to locating

    block centre RH (755mm)

    Structure centre line to locating

    block centre LH (755mm)

    3.14.3 Produce rails to Schade drawing 6607_01_008

    using Gantrail welding instructions and hardware.

    3.14.4 Position Rails onto Platform Structure at 1435

    2mm gauge equally spaced about the

    longitudinal centre line.

    3.14.5 Fasten rail ends and install clips to Schade

    drawing 6100_02_003 (section E-E and F-F) and

    Gantrail instructions.

    3.14.6 The Platform Walkways are to be assembled in

    accordance with Schade drawings 6100_02_003

    & 6198_02_002, and document 20.312_D04.

    Note - the platform walkways can be

    assembled at any stage. To allow access into

    the foundation pit area (to adjust drives and

    supports or set up limit switches etc.) it will

    be better to assemble the walkways at a later

    stage.

    3.14.7 Install the Wheel Locating Brackets

    (6100_02_003 items 19) and Angles

    (6100_02_003 items 20 & 21) to Schade drawing

    6100_02_003 and document 20.312_D04.

    3.15 Alignment of Platform Supports

    Refer to the following Schade drawings:-

    Gantrail

    WPS

    Gantrail

    instructions

    A1

    A1

    A1

    A1

    A1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 26 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    6115_02_003, Assembly of Platform Support

    3.15.1 Using the dimensions recorded in 3.14 above; adjust the height of the Platform Supports

    (6115_02_003) such that the top face of the

    Platform will be at TOC level when installed.

    Hand tighten Platform Support M30 foundation

    studs and adjust packers as required.

    3.15.2 Using the dimensions recorded in 3.14 above; adjust the Platform Supports (6115_02_003) such

    that the Platform longitudinal centre line will

    align with the main track centre line when

    installed.

    3.15.3 Using the dimensions recorded in 3.14 above; adjust the Platform Supports (6115_02_003) such

    that the Platform transverse centre line will align

    with the Tippler centre line when installed.

    Note further/final adjustment will be carried out

    at a later stage to correctly align the platform rails

    with the land rails.

    3.16 Platform Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 10)

    6100_02_003, Assembly of Platform

    6035_02_007, Assembly Of 14m Pivot Frame

    Tippler

    6115_02_003, Assembly of Platform Support

    6095_02_002, Assembly of Pivot Frame Tippler

    Structure

    3.16.1 With reference to Schade drawing 6100_02_003

    section D-D, position Pivot Rollers (item 6,

    6712_01_001) into the End Ring toe slot. Locate

    at bottom of slot and centrally across the width.

    A1

    A1

    A1

    W1

    W1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 27 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.16.2 Lift the Platform sub-assembly off its temporary supports and onto the Platform Supports

    6115_02_003.

    3.16.3 Build Pivot Roller assemblies at both ends to

    Schade drawing 6100_02_003 section D-D and

    lubricate Bushes via the temporary grease

    nipples.

    Note Safety Hooks (6100_02_003 items 12

    and13) are handed.

    3.16.4 Check at both End Rings that the Pivot Rollers

    are central within the 150mm thick End Ring toes

    per Schade drawing 6035_02_007 section Y-Y.

    Adjust the position of the Platform Supports

    (6115_02_007) if necessary to achieve this.

    3.16.5 With reference to Schade drawing

    6095_02_002, replace Packers (item 10) with

    wooden blocks that will limit Platform rotation to

    110mm.

    On completion of this section re install Packers.

    3.16.6 Under controlled conditions, release the Tippler

    restraints to allow the Tippler structure to rotate

    in the anti-clockwise direction (viewed from the

    full wagon entry end) until one of the End Ring

    slots just contacts the Pivot Roller. Adjust the

    height of the Platform at the other End Ring so

    that both Pivot Rollers are contacted at the same

    angle of Tippler rotation.

    Repeat to confirm that both Pivot Rollers are

    contacted and picked up at the same angle.

    3.16.7 Under controlled conditions, release the Tippler

    restraints to allow the Tippler structure to rotate

    in the anti-clockwise direction (viewed from the

    full wagon entry end) and pick up the Platform.

    Continue rotation until both Support Rollers

    (6100_02_003 item 6) are just clear of the Roller

    Support Ramps (6115_02_003 item 3).

    X

    Procedure

    X

    Procedure

    X

    Procedure

    A1

    A1

    A1

    R1

    W1

    A1

    R1

    W1

    W1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 28 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.16.8 Under controlled conditions, rotate the Tippler

    in the opposite direction until the Upper Locating

    Blocks (6100_02_003 item 18) are almost in

    contact with the Lower Locating Blocks

    (6115_02_003 item 2).

    Adjust the positions/heights of the Lower

    Locating Blocks to ensure a smooth engagement

    as the Upper Locating Blocks lower.

    3.16.9 Return the Tippler to its start position and

    restrain against further rotation.

    Notes-

    The above setting up work can be carried out after completion of the electrical and

    hydraulic installations.

    The Upper and Lower Locating Blocks are to be set in a position dictated by the pick up

    angle of the Pivot Rollers (6100_02_003 item

    11) in the End Ring toe slots. The principle is

    that the Upper Locating Blocks will

    automatically determine the correct location

    of the Lower Locating Blocks, i.e. where the

    Tippler geometry needs them to be.

    3.16.10 Fully tighten Platform Support M30 foundation

    studs and grout in position.

    Weld Washers (6115_02_003 item 6) per

    drawing requirements.

    3.17 Thrust Pads Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 11)

    6003_02_003, General Arrangement of Wagon

    Unloading System

    6723_02_001, Thrust Pad

    3.17.1 With reference to Schade drawing 6003_02_003

    A1

    A1

    A2

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 29 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    section L-L, position Thrust Pads with a 10mm

    gap at each end of the Platform.

    Cast in position with full strength concrete

    ensuring that the 10mm gap is maintained.

    3.18 Tippler Ballast

    Refer to the following Schade drawings:-

    6975_00_001, Tippler Erection Sequence

    Diagram (step 12)

    6186_02_002, Assembly of Tippler Ballast

    3.18.1 End Ring fixing holes for the Ballast Plates have

    been drilled during workshop assembly and

    match marked.

    Using the workshop match marking, install the

    Tippler Ballast to Schade drawing 6186_02_002.

    3.19 Cable Loop

    Refer to the following Schade drawings:-

    6105_02_003, Assembly of Tippler Cable Loop

    6003_02_003, General Arrangement of Wagon

    Unloading System

    3.19.1 Install Cable Loop components to above

    drawings.

    3.20 Tippler Limit Switches Refer to the following Schade drawing:-

    6106_02_003, Assembly of Tippler Limit

    Switches

    3.20.1 Install Limit Switch components to above

    drawing.

    Workshop

    records

    A1

    A1

    A1

    W1

    A2

    A2

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 30 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.21 Tippler Encoders

    Refer to the following Schade drawing:-

    6103_02_007, Assembly of Tippler Drives (RH)

    3.21.1 Install Encoder components to above drawing.

    3.22 Tippler Clearance Sensors

    Refer to the following Schade drawing:-

    6107_02_003, Assembly of Tippler Clearance

    Sensors

    3.22.1 Install Clearance sensor components to above

    drawing.

    3.23 Stockpile Sensors

    Refer to the following Schade drawing:-

    6133_02_001, Assembly of Stockpile Sensors

    3.23.1 Install Stockpile sensor components to above drawing.

    3.24 Tippler Hydraulics

    Refer to the following Schade drawing:-

    6400_00_002, Assembly of Tippler Hydraulics

    Read this drawing in conjunction with the Bosch

    Rexroth Hagglunds drawings and installation

    instructions.

    3.24.1 Install Tippler Hydraulics in accordance with the

    Bosch Rexroth Hagglunds drawings and

    installation instructions.

    Note- at a given stage within this installation, the

    drive brake release screws are to be removed and

    the brakes applied.

    3.24.2 Review and verify the installation.

    X

    Supplier

    documents

    A1

    A1

    A1

    R1

    A1

    A2

    A2

    A2

    A2

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 31 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.25 Dust Suppression System

    Refer to the following Schade drawing:-

    6495_00_001, Assembly of Dust Suppression

    System

    Read this drawing in conjunction with the Nalco

    Enviroflo drawings and installation instructions.

    3.25.1 Install Dust Suppression System in accordance

    with the Nalco Enviroflo drawings and

    installation instructions.

    3.25.2 Review and verify the installation

    3.26 Exit Run-Back Stop

    Refer to the following Schade drawings:-

    6058_02_004, Assembly of Exit Run-Back Stop

    (Manual)

    6460_00_009, Wagon Unloading System

    Foundation Details and Loadings

    3.26.1 Workshop assembly of the Run-Back Stop has

    been carried out, followed by some disassembly.

    To install the Run-Back Stop in its foundation pit

    below the main track rails, some further

    disassembly may be required.

    All components must be match marked prior to

    this site disassembly.

    3.26.2 Align the exit and entry main track rails with the

    Tippler Platform rails and check that rail gauge is

    maintained.

    Check that there is a max. platform to land rail

    gap of 10mm.

    Check that there is no vertical or side step at the

    platform to land rail gaps.

    X

    Supplier

    documents

    R1

    A1

    A1

    A1

    A1

    A2

    A1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 32 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    3.26.3 Install Run-Back Stop to Schade drawing

    6058_02_004.

    Check the following:-

    Stop (item 4) is 69mm min. above the top of both rails.

    Stop can be pushed down by hand (without lever moving), representing a

    wagon rolling over it.

    Stop lowers when the handle is raised.

    Foundation bolts (6058_02_004 item 36) are fully tightened.

    3.26.4 After installation of the Run-Back Stop, re

    check its operation and the platform to rail

    alignment.

    Do not install full strength concrete until the

    Wagon Unloading System has been fully

    commissioned.

    3.27 Tippler & Run-Back Stop Lubrication

    Refer to the following Schade drawing:-

    6410_00_002, Assembly of Tippler and Run-

    Back Stop Lubrication

    Read this drawing in conjunction with the Bijur

    Delimon drawings and installation instructions.

    3.27.1 Install Lubrication System in accordance with

    the Bijur Delimon drawings and installation

    instructions.

    Guards may need to be manufactured (determined

    during installation) to protect exposed pipes etc.

    3.27.2 Review and verify the installation.

    3.28 Tippler and Run-Back Stop Electrics

    Refer to the following Schade drawing and

    document:-

    X

    Suppliers

    documents

    A1

    A1

    R1

    A1

    A1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 33 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    6340_00_002, Assembly of Tippler and Run-

    Back Stop Electrics

    Read this drawing in conjunction with the Iconsys

    drawings and installation instructions.

    20.312_D26, Electrical Installation Method

    Statement

    3.28.1 Install Electrics in accordance with the above

    drawings and document.

    3.28.2 Review and verify the installation.

    X

    Suppliers

    documents

    R1

    A1

    A1

  • Contract Name/Number- Document No. Revision - 01

    SPCC ILO PERU/20.312 D25 Page 34 of 34

    METHOD STATEMENT This Method Statement is not to be copied or disclosed to third parties, unless otherwise agreed in writing.

    This Method Statement is the property of Schade Lagertechnik GmbH

    Ref. Description of Operation

    Operation

    Complete (sign and date)

    SPCC/Installer

    Document

    Required (enter identity

    where marked)

    Verification (sign and date

    where indicated)

    SPCC/

    Installer

    Schade

    Technical

    Advisor

    4. DIMENSIONAL CHECK

    In conjunction with Schade Technical Advisor,

    carry out checks and record important

    dimensions.

    The selection of these dimensions is to be agreed

    with the Schade Technical Advisor and used for

    future checks of structures and mechanicals.

    5. FINAL INSPECTION

    Final inspection to confirm that the equipment,

    including paintwork, is in its correct state and all

    extraneous materials have been removed.

    6. FINAL DOCUMENT CHECK

    Final document check to verify that all specified

    operations have been completed with the correct

    results, all supporting records are available and

    any reported non-conformities have been

    resolved.

    Record on

    drawings

    X

    Collate all

    records

    A2

    A1

    R1

    A2

    A2

    R2