Objectives Understand the motivation for technical review.
Become acquainted with “best practices” for “industrial strength” formal technical review.
Begin the journey toward 'optimal' review in your own practice.
(3)
Optimal Review For me, an 'optimal' review will:•find all important defects•give all reviewers deep insight into the code•enable the author to improve the code•all with least possible effort
In other words:•Optimal quality improvement•Optimal knowledge acquisition•With lowest possible cost
Normally, though, it’s “pick any two”.
(4)
Families of Review Methods
Walkthroughs
Minimal overhead
Developer training
Quick turnaroundDefect discoveryAmbiguity resolutionTraining
Method Family
Typical Goals Typical Attributes
Little/no preparation
No formal process
No measurement
Technical Reviews
Some formal process
Multiple stages
Wide range of discussion
Inspections
Detect and remove all defects efficiently and effectively.
Very formal process
Measurement
Verification
(5)
Methods vs. Optimality Walkthroughs:•Cost: very low•Knowledge transfer: undependable•Quality improvement: undependable
Technical reviews:•Cost: moderate•Knowledge transfer: better•Quality improvement: at least some
Inspection:•Cost: high (and not necessarily ‘least possible’)•Knowledge transfer: almost guaranteed.•Quality improvement: almost guaranteed
(6)
1. Reviews improve schedule predictability.
2. Reviews reduce rework.•Rework accounts for 44% of dev. cost!•Reqs (1%), Design (12%), Coding (12%), Testing (19%)
3. Reviews are pro-active tests.•Find errors not possible through testing, such as Errors of Omission (i.e. unimplemented requirement)
4. Reviews are training.•Domain, corporate standards, group.
What reviews do that testing doesn't
No Revs.
Revs
Req Design Code Test
R R RReq Design Code Test
(7)
Industry experience Aetna Insurance Company:•FTR found 82% of errors, 25% cost reduction.
Bell-Northern Research:•Inspection cost: 1 hour per defect.•Testing cost: 2-4 hours per defect. •Post-release cost: 33 hours per defect.
Hewlett-Packard•Est. inspection savings (1993): $21,454,000
IBM (using Cleanroom)•C system software•No errors from time of first compile.
(8)
There are many different kinds of review
TekInspect
Development MethodNon-Cleanroom Cleanroom
FTRinFTR
CodeInspection(Fagan76)
Inspection(Gilb93)
2-PersonInspection(Bisant89)
N-FoldInspection(Martin90)
Walkthrough(Yourdon89)
Verification-basedInspection(Dyer92)
ActiveDesignReviews(Parnas85)
FTArm(Johnson94)
ICICLE(Brothers90)
Scrutiny(Gintell93)
CAIS(Mashayekhi94)
ManualTool-Based
CodeReading(McConnell93)
SoftwareReview(Humphrey90)
Phased Insp.(Knight93)
(9)
Inspection: the most formal review
Preparation
Orientation
Planning
Review Meeting
Rework
Verify Verify product/process quality
Correct defects.
Consolidate issues.
Check product, note issues.
Present product, process, goals.
Choose team, materials,
dates.
(10)
Planning
Objectives•Gather review package: work product, checklists, references, and data sheets.•Form inspection team.•Determine dates for meetings.
Planning Orientation Preparation Review Mt. Rework Verify
(11)
Orientation
Objectives•Author provides overview.•Reviewers obtain review package.•Preparation goals established.•Reviewers commit to participate.
Planning Orientation Preparation Review Mt. Rework Verify
(12)
Preparation
Objectives•Find maximum number of non-minor issues.
Planning Orientation Preparation Review Mt. Rework Verify
(13)
Example Issue Classification
Critical•Defects that may cause the system to hang, crash, produce incorrect results or behavior, or corrupt user data. No known work-arounds.
Severe•Defects that cause incorrect results or behavior with known work-arounds. Large and/or important areas of the system is affected.
Moderate•Defects that affect limited areas of functionality that can either be worked around or ignored.
Minor•Defects that can be overlooked with no loss of functionality.
(14)
Review Meeting
Objectives•Create consolidated, comprehensive listing of non-minor issues.•Provide opportunity for group synergy.•Improve reviewing skill by observing others. •Create shared knowledge of work product.
Planning Orientation Preparation Review Mt. Rework Verify
(15)
Rework
Objectives•Assess each issue, determine if it is a defect, and remove it if necessary.•Produce written disposition of non-minor issue.•Resolve minor issues as necessary.
Planning Orientation Preparation Review Mt. Rework Verify
(16)
Verify
Objectives•Assess the (reworked) work product quality.•Assess the inspection process.•Pass or fail the work product.
Planning Orientation Preparation Review Mt. Rework Verify
(17)
ICS Software Engineering
Technical Reviews
(18)
Goals for our Tech. Reviews 1. Learn how to obtain useful feedback from classmates about your software system.
2. Learn how to critically read and evaluate code written by another developer.
3. Learn the difference between low-impact, “waste of time” reviews and high-impact, “would have never noticed this myself” reviews.
4. Learn that reviewing other code can be an effective way to improve your own coding skills.
(19)
Initial approach: Checklist-based technical
review Use a checklist to:•focus reviewer attention.•specify the concerns of the review
Write down reviewer comments to:•provide a clear record of reviewer feedback.•assess coverage of review.
Go over reviewer comments with author to:•Clarify meaning of comments. •Assess validity.•Provide opportunity for new issues to arise.